Question 131 · 220 in bank
Risk is configured by default, to calculate Risk = High for a change that is scheduled with only 3 days lead time. Your customer’s change policy requires that changes be requested with 5 days lead time. How would you satisfy this requirement?
Show answer
Answer: E
Explanation
Correct Ans is "E" . Update the risk condition "Insufficient lead time". We can change the filter conditions inside the risk condition- Planned start date - relative - on o before- 5 days- from now
Source: Adapted from community discussion — Amr94