Question 191 · 1401 in bank
A project team is in the planning stage and has prepared a list of activities and completed sequencing the activities. During a review, the team noted that there is a dependency missing between: • Test the product • Release to customer According to the quality management plan, the product must be tested before being released. How should the project manager enter this dependency?
Show answer
Answer: B
Explanation
The correct way to enter this dependency is B. Finish to start. This is because the "Test the product" activity must be finished before the "Release to customer" activity can start. In a Finish to Start dependency, the initiation of the successor (in this case, releasing the product to the customer) is dependent on the completion of the predecessor (testing the product). This type of dependency is very common in project management, especially in cases where a certain phase or component of the project must be completed before the next phase can commence.