Question 151 · 1401 in bank
During a project status meeting with senior managers, the project manager gives an update about the status of a deliverable. Some of the senior managers claim not to know about the deliverable. What should the project manager do next?
Show answer
Answer: B
Explanation
In this situation, where senior managers claim not to know about a deliverable during a project status meeting, the project manager should take steps to ensure that all stakeholders have a clear understanding of the project's scope and deliverables. The appropriate next steps would be: B. Meet with these stakeholders to review the project charter: This is the most immediate and effective approach. The project charter is a key document that outlines the project’s objectives, scope, deliverables, and stakeholders. Reviewing the project charter with the senior managers will help clarify any misunderstandings or gaps in their knowledge about the deliverables. It also provides an opportunity for the project manager to reinforce the project's objectives and deliverables and ensure alignment among the senior stakeholders.
Source: Adapted from community discussion — Delab202