Question 171 · 1401 in bank
A project is in the final stages, and a key stakeholder demands a change to a product feature that will add 2 weeks to the critical path. What should the project manager do?
Show answer
Answer: B
Project Management Professional1,401 questions across 141 pages are complete and free, with no account or card.
1401 questions in this bank
Free access · progress saved on this device
A project is in the final stages, and a key stakeholder demands a change to a product feature that will add 2 weeks to the critical path. What should the project manager do?
Answer: B
A project manager is newly assigned to the second phase of an ongoing project. During the implementation, a defect occurred and no one knows how to fix it, as the former engineering team has moved to another project. The customer warns that previously. this defect negatively affected the project schedule. What should the project manager do first?
Answer: A
A project manager has taken over an agile project. There have been several issues during product development due to unclear product requirements. How should the project manager resolve this issue?
Answer: B
When dealing with unclear product requirements in an Agile project, the most effective approach is to involve both the project team and the product owner in finding a solution. Therefore, the best option would be: B. Gather the project team and product owner to find a solution design. This approach aligns well with Agile principles, which emphasize collaboration, continuous feedback, and adaptability. By bringing together the project team and the product owner, the project manager can facilitate a discussion to clarify requirements, address ambiguities, and ensure that everyone has a shared understanding of the project goals and deliverables. This collaborative effort can lead to the refinement of the product backlog and more effective sprint planning, ultimately leading to better outcomes.
Source: Adapted from community discussion — Delab202
A project manager has just been assigned to a new project. The project manager's first task is to present the project benefits to the stakeholders. Which three items should form part of the presentation? (Choose three.)
Answer: ADE
Risks associated with achieving the target benefits (A): This is crucial because stakeholders need to be aware of potential challenges or obstacles that could impact the realization of the project's benefits. Including risks in the presentation helps in setting realistic expectations and prepares stakeholders for possible contingencies. Expected business value (D): This is arguably the most important component of the presentation. The project manager should articulate how the project will contribute to the business’s goals, objectives, or bottom line. This includes detailing the tangible and intangible benefits that the project is expected to deliver. Metrics to measure benefits throughout the project (E): It is important to establish how the success of the project will be measured. Presenting the metrics for measuring benefits not only shows a plan for tracking progress but also helps in maintaining stakeholder confidence throughout the project lifecycle by providing a way to assess whether the project is on track to deliver its intended benefits.
Source: Adapted from community discussion — Delab202
A project has been running successfully for 2 months. At a regular project meeting, the team raises several potential obstacles to future progress. The obstacles include vendor delivery performance, technical performance of a subsystem, and conflict with another division of the organization. What should the project manager do next?
Answer: C
An agile facilitator has gathered a team for a new project. This team and facilitator have not yet worked on a project together. How should the facilitator proceed?
Answer: B
When working with a new team on a project, the Agile Facilitator should start by holding a team charter discussion. This session helps the team establish a shared understanding of the project's purpose, goals, and expectations. During the session, the team will discuss the scope of the project, the stakeholders involved, and the team's roles and responsibilities. This discussion will help the team align on the project's objectives, establish a foundation of trust, and identify potential risks and challenges.
Source: Adapted from community discussion — Hung3102
A project team was asked to resume development activities on a project that was suspended for a few months due to the fast-changing environment and conditions. What should the project lead do?
Answer: A
When a project is resumed after a suspension, especially in a fast-changing environment, it's crucial to reassess and align the project's goals, priorities, and plans. Here are the best steps for the project lead: Review the items remaining in the backlog with the project team (Option A): This is a critical step. The project team, being closely involved in the project execution, is best positioned to understand the technical details, dependencies, and complexities of the backlog items. They can provide valuable insights into what has changed, what remains relevant, and what needs to be reprioritized or adjusted.
Source: Adapted from community discussion — Delab202
During project execution, a project manager discovers that the budget at completion has shifted significantly and is higher than expected. What should the project manager do?
Answer: A
When the budget at completion has shifted significantly and is higher than expected, it's important for the project manager to perform a root cause analysis. This involves investigating the factors and events that have led to the budget variance. By identifying the root causes, the project manager can address the underlying issues and take corrective actions to bring the project back on track. Adjusting stakeholder expectations and negotiating changes may be part of the response, but understanding the root causes is a crucial first step.
Source: Adapted from community discussion — Abdelmonm
In a project using a hybrid approach, the performance of the team was consistently excellent during the predictive stages. When the iterations began, however, the team members started to show signs of low commitment, conflicts, and confusion, resulting in low morale. What should the project manager do to handle this situation?
Answer: A
The team already worked together before as stated in the question so they know each other, the issue started with they started to use Agile. so they need to understand how Agile works
Source: Adapted from community discussion — chlaithem
During the daily standup meeting that is assessing progress against the current sprint, a team member reports some delays due to a component managed by an external vendor. How should the project manager address the team member’s concern?
Answer: B