A project manager has been assigned to a project that involves building 100 wells for a small community that is urgently in need or access to water. What should the project manager do next?
Show answer
Answer: A
Project Management Professional1,401 questions across 141 pages are complete and free, with no account or card.
1401 questions in this bank
Free access · progress saved on this device
A project manager has been assigned to a project that involves building 100 wells for a small community that is urgently in need or access to water. What should the project manager do next?
Answer: A
A project manager has been assigned to manage multiple agile project teams. The project manager wants to empower the teams and make them self-organizing. What should the project manager do to create a positive environment?
Answer: A
A project manager discovered that a component on the critical path is in danger of delay due to continuous disagreements between two developers. This personality-related issue can’t be resolved by the team. What should the project manager do?
Answer: C
Asking the team to take a vote can have a knock-on effect on the behavior of the two developers against the team in which they are part of. Besides the question stated the “issue can’t be resolved by the team” so that’s ruled out B. Delaying the development of the component is not a good option, so A is wrong. D would have been a good answer, but since it’s a continuous disagreement between the two developers even with possible intervention with the Project Manager to resolve their conflict. Hence, the last course of action to answer this question is to escalate the issue with the HR Manager, so answer is C.
Source: Adapted from community discussion — Sunshine2022
An agile coach and technical writer for a globally distributed agile team are in a country with a 9-hour time zone difference from the agile team. The agile coach and project lead disagree on the timing for the daily standup. The project lead thinks the standup should be at 10:00 am local time, but the agile coach and technical writer feel that is an inconvenient time for them. How does the project lead ensure adherence to agile practices?
Answer: C
In a weekly status meeting with the client, the project manager asks each team member to present how their deliverables are impacting the customer's final product requirements. Which leadership skill is the project manager applying?
Answer: C
In this scenario, the project manager is **having a holistic and systemic view (Option C)**. By asking each team member to present how their deliverables are impacting the customer's final product requirements, the project manager is ensuring that everyone understands the big picture and how their work contributes to the overall project goals. This approach helps to align the team's efforts and ensures that everyone is working towards the same objectives. It's a key leadership skill that can help to drive project success.
Source: Adapted from community discussion — josephsafiran
A project manager receives a suggestion from a team member for improving the product attributes without impacting the schedule or cost. This will add value to the project and the customer. What should the project manager do?
Answer: B
A construction company recently won the bid for a project to build a cable bridge. A project charter has been prepared and a project manager has been assigned. The project manager is creating a work breakdown structure (WBS) for the project. To what level should the project manager decompose their project?
Answer: A
During the third iteration of a project, the main sponsor retired from the company, and a new sponsor was appointed. The new sponsor is not familiar with the agile approach for project delivery, which leads them to request more control over the project team. What should the project manager do?
Answer: A
A project manager is working on a global project. One team member is from a different country and is unable to attend project meetings on a regular basis. Because of this, other team members have started questioning the need for the project meeting. This issue is affecting the time line deliverable and quality parameters. What should the project manager do to manage the project deliverables?
Answer: D
The issue is not that a remote person csnt always join, the issue is that others now that its okay to slack off in the meeting. We need to address this by adding meaning to the meeting. We can do this by explaining the purpose using an Agenda
Source: Adapted from community discussion — 6thEditionAndy
A medium-sized company has been exploring new marketing tactics with regard to launching a new product. New product creation is no small task. In the end, it was too big of an expenditure for the company to undertake. What should the project manager do in the future when working on new product projects?
Answer: B