Question 201 · 1401 in bank
Halfway through project execution, stakeholders ask for equipment that was expected to be procured. The project manager explains that the equipment was purchased, but differs from what the stakeholders are currently asking for. This is because the initial requirements were changed during a previous meeting. What should the project manager have done to avoid this situation?
Show answer
Answer: D
Explanation
D is the answer as it shows better execution of communication management plan. B is part of monitor and control phase which is reactive if plan/execution is not proper.
Source: Adapted from community discussion — certificate988