The project sponsor recently requested that a vendor begins working toward adopting a hybrid approach. In response, the vendor hired a project manager experienced in agile for the project. What does that project manager need to do to make the team work in a collaborative way?
Show answer
Answer: A
Explanation
Mentoring provides direct and personal support to team members, helping them understand and adapt to the hybrid approach. This one-on-one or small group interaction can address specific concerns and facilitate a deeper understanding of agile practices. A mentor helps build trust within the team by fostering open communication and collaboration. As team members feel more supported and confident, they are more likely to work together effectively. Therefore, allocating time to mentor the team directly addresses the immediate need for building a collaborative working environment and is the most practical and impactful step the project manager can take.
Source: Adapted from community discussion — UppersquareCapital