Question 111 · 1401 in bank
A project manager is developing the stakeholder register and is having trouble understanding the motivation of some of the stakeholders. What should the project manager do to get this information?
Show answer
Answer: D
Explanation
A business case does not show the motivations of the stakeholders. it may show some of their needs, but not their specific motivations. The question also says the PM is having issues with SOME not all so the PM does not have to meet all, just SOME. I'll choose one-on-one with those SOME
Source: Adapted from community discussion — Ade1981