Question 311 · 497 in bank
Which is the most accurate description of a backlog in agile?
Show answer
Answer: B
Certified Associate in Project Management497 questions across 50 pages are complete and free, with no account or card.
497 questions in this bank
Free access · progress saved on this device
Which is the most accurate description of a backlog in agile?
Answer: B
Which three of the following are key traits of a project leader? (Choose three.)
Answer: ABD
What is the process of determining the stakeholders impacted by a business problem or opportunity?
Answer: D
A project manager joined a company to replace someone that left the project. There was no hand over, but the previous project manager developed a detailed schedule and the project team completed some project deliverables. The team is not colocated and some of the team members are former interns that were recently employed full time. What is the most suitable project delivery method?
Answer: A
A project manager is responsible for delivering new software for their company. Based on previous experiences, the project manager decides to use the dynamic systems development method (DSDM). The project manager will use this method to prioritize the scope to meet project constraints. Which elements are included in the DSDM framework?
Answer: C
What should the project manager use to evaluate the politics and power structure among stakeholders inside and outside of the organization?
Answer: A
The answer is A. Expert Judgment is a term that refers a specifically to a technique in which judgment is made based upon a specific set of criteria and/or expertise that has been acquired in a specific knowledge area, or product area, a particular discipline, an industry, etc.
Source: Adapted from community discussion — meg002
An organization's annual report indicates that there needs to be a new strategy that prioritizes long term goals and repetitive solutions. What project methodology should this organization consider?
Answer: C
Predictive methodology prioritizes long-term goals. Predictive methodologies are well-suited for projects with clearly defined objectives and deliverables, which often align with long-term organizational goals. Repetitive solutions: Predictive approaches excel in projects that involve well-understood processes and repeatable tasks, allowing for efficient planning and execution.
Source: Adapted from community discussion — Vangelis_1980
A project team member is reviewing the scope of a task with an end user and realizes that requirements have changed. Which project artifact should be used in this situation?
Answer: A
A key stakeholder has left the project management team. The team now has a new key stakeholder who is requesting project reports from team members out of sequence. What should the project manager do first?
Answer: B
A new project manager has been assigned to an ongoing project. What will the project manager use to identify the responsibilities of the stakeholders in the project?
Answer: A
Keyboard:J Kmove between questionsA–Dselect an answerRshow or hide the answer← →change page
CAPM practice, question 311. 497 questions available.