In an agile or adaptive environment, when should risk be monitored and prioritized?
Show answer
Answer: C
Certified Associate in Project Management497 questions across 50 pages are complete and free, with no account or card.
497 questions in this bank
Free access · progress saved on this device
In an agile or adaptive environment, when should risk be monitored and prioritized?
Answer: C
A new project was approved by the project management office (PMO), and the scope of the project is to build a new detachable classroom. What delivery method and artifacts should the project manager use to deliver this project?
Answer: C
Which factors should be considered for cross-cultural communication?
Answer: D
D- per pmbok 6th, 10.1.2.4 ( communication models) page 373. Cross cultural communication ( a tool/technique of Plan Communication Management) incorporates the idea that the message itself and how it is transmitted are influenced by the senders current emotional state, knowledge, background, personality, culture and biases. Similarly the receivers emotional state ,knowledge, background, personality, culture and biases will influence how the messages is is received and interpreted.
Source: Adapted from community discussion — Zmfoutch
Which of the following does a portfolio combine?
Answer: C
The procurement requirements for a project include working with several vendors. What should the project manager take into consideration during the Project Procurement Management processes?
Answer: C
The answer is C: from p 683 PMBOK 6th Ed. X5.9 PROJECT PROCUREMENT MANAGEMENT Considerations for tailoring project procurement management include but are not limited to: - Complexity of procurement. Is there one main procurement or are there multiple procurements at different times with different sellers that add to the complexity of the procurements?
Source: Adapted from community discussion — sham222
A team member, who is close to an influential stakeholder, has joined the project team. The stakeholder is routing requests for multiple reports through the new team member, and the team member reaches out to the project manager regarding this. What should the project manager do first?
Answer: C
A project receives budget approval, but the risk of extra costs is expected. Which of these inputs should the project manager check in order to make a qualitative risk analysis?
Answer: A
All testing on a project has been performed successfully and all acceptance criteria have been met. What is the next step?
Answer: A
What is one of the main purposes of the project charter?
Answer: A
How does a requirements traceability matrix help to determine whether a product is ready for delivery?
Answer: B
Keyboard:J Kmove between questionsA–Dselect an answerRshow or hide the answer← →change page
CAPM practice, question 371. 497 questions available.
Version 1.0.0. How we source questions