Question 241 · 497 in bank
A project manager is working on an estimate. The project team is estimating each work package and then finding the total of all the work packages. Which technique is the project manager using?
Show answer
Answer: C
Explanation
Pg 244 PMBOK 6th Bottom-up estimating is a method of estimating a component of work. The cost of individual work packages or activities is estimated to the greatest level of specified detail. The detailed cost is then summarized or “rolled up” to higher levels for subsequent reporting and tracking purposes.
Source: Adapted from community discussion — Raindrop79