Question 191 · 497 in bank
If a project manager effectively manages project knowledge, a key benefit is that:
Show answer
Answer: D
Explanation
The correct answer is D. New knowledge is added to organizational process assets. Effective management of project knowledge involves capturing and documenting lessons learned, best practices, and other valuable insights gained throughout the project. By doing so, this knowledge becomes part of the organizational process assets, which are resources, tools, and knowledge that can be used by the organization in future projects. This contributes to organizational learning and continuous improvement. While options A, B, and C are important aspects of project management, they don't specifically capture the broader organizational benefit of adding new knowledge to the organizational process assets.