Question 41 · 181 in bank
Who creates a Product Backlog Item's estimate?
Show answer
Answer: A
Professional Scrum Master I181 questions across 19 pages are complete and free, with no account or card.
181 questions in this bank
Free access · progress saved on this device
Who creates a Product Backlog Item's estimate?
Answer: A
Who starts the Daily Scrum?
Answer: B
You are the Scrum Master on a newly formed Scrum Team. Which three of the following activities would probably help the team in starting up? (Choose three.)
Answer: BEF
A Development Team selects a set of Product Backlog items for a Sprint Backlog with the intent to get the selected items `Done` by the end of the Sprint. Which three phrases best describe the purpose of a definition of `Done`? (Choose three.)
Answer: CEF
Select two ways in which technical debt impacts transparency. (Choose two.)
Answer: BC
Which of these may a Development Team deliver at the end of a Sprint?
Answer: C
How much of the Sprint Backlog must be defined during the Sprint Planning event?
Answer: C
Who is responsible for managing the progress of work during a Sprint?
Answer: B
A Development Team is required to deliver a done Increment by the end of a Sprint. Select two statements that explain what `Done` means. (Choose two.)
Answer: CE
What two factors are best considered when establishing the Sprint length? (Choose two.)
Answer: BD