Question 11 · 181 in bank
Which of the following is required by Scrum?
Show answer
Answer: A
Professional Scrum Master I181 questions across 19 pages are complete and free, with no account or card.
181 questions in this bank
Free access · progress saved on this device
Which of the following is required by Scrum?
Answer: A
What is the purpose of a Sprint Review?
Answer: B
Who determines when it is appropriate to update the Sprint Backlog during a Sprint?
Answer: B
Who must attend the Daily Scrum?
Answer: B
When do Development Team members take ownership of a Sprint Backlog item? (Choose the best answer.)
Answer: C
True or False: The purpose of a Sprint is to produce a valuable, useful Increment.
Answer: A
Who creates the definition of `Done`?
Answer: B
Five new Scrum Teams have been created to build one product. A few of the developers on one of the Scrum Teams ask the Scrum Master how to coordinate their work with the order teams. What should the Scrum Master do?
Answer: B
Which two things should the Development Team do during the first Sprint? (Choose two.)
Answer: CE
What are three ways Scrum promotes self-organization? (Choose three.)
Answer: BDE
Keyboard:J Kmove between questionsA–Dselect an answerRshow or hide the answer← →change page
PSM I practice, question 11. 181 questions available.
Version 1.0.0. How we source questions