Question 611 · 1401 in bank
A project team created user stories after understanding the customer requirements. As the project progresses, the project manager observes that there are too many change requests. The team feels that the outcomes they are working on are not aligned with the customer requirements. What should the project manager do?
Show answer
Answer: B
Explanation
From ChatGPT: B. Arrange for a workshop with the customer to understand the business values expected from the outcomes. The project manager should arrange a workshop with the customer to clarify and understand their business values and requirements. This will help to ensure that the team is aligned with the customer's expectations and can reduce the number of change requests. Involving the customer in the process will also help to build trust and improve communication between the team and the customer. Referring to the configuration management knowledge base may provide some insights, but it may not address the specific concerns and issues of the current project. Including a representative from the customer to work collaboratively with the team can also be helpful, but it may not address the underlying issue of misaligned expectations. Acknowledging that the current team needs improvement and hiring more qualified team members may be premature without understanding the root cause of the issue.
Source: Adapted from community discussion — YOLO28