Question 661 · 1401 in bank
A project manager is working on a major construction project. Part of the agreed-upon plan was to use a cloud-based system with a server that runs on high- speed internet service since most of the team members work virtually. The company needs to reduce operating costs as much as possible and management insists that the project will now use a system running on a conventional dial-up service. What should the project manager do next?
Show answer
Answer: B