A project is behind schedule because of a delayed equipment installation. This is affecting many other activities. The manager responsible for the equipment delivery notified the project manager that there is a capacity issue for the team doing the installation. What should the project manager have done to prevent this situation from happening?
Show answer
Answer: C
Explanation
The correct answer is C. Conducted periodic reviews with the manager on resource availability. By conducting periodic reviews with the manager on resource availability, the project manager could have identified the capacity issue earlier and taken proactive measures to mitigate the risk of a delayed equipment installation. This could have included exploring alternative installation teams or adjusting the project schedule to account for the delay.