Question 561 · 1401 in bank
A project manager is assigned to a major construction project. The project is critical to the city's population, and especially to the local government official who committed to delivering the project on time as an election promise. A new project sponsor has been assigned and wants to include aspects that the previous project sponsor did not support. What should the project manager do next?
Show answer
Answer: A
Explanation
This will help to ensure that both the project manager and the new project sponsor are on the same page regarding the project scope and objectives
Source: Adapted from community discussion — akcisa_79