Question 641 · 1401 in bank
A new engineer was assigned to a project. Although the engineer has adequate skills for the job, they always wait for authorization from the project manager before acting. What should the project manager do?
Show answer
Answer: B
Explanation
The best course of action for the project manager in this situation would be option B: Determine the appropriate level of decision-making authority and empower the engineer.
Source: Adapted from community discussion — Alizade