Question 671 · 1401 in bank
A client wants to create an innovative software for the travel industry using an agile approach. A project manager from the company was assigned to work on the details and estimates as requested by the client. What should the project manager do before sending the information to the client?
Show answer
Answer: D
Explanation
This is D. You can't provide a prototype, at least a good one without consulting with the team first or even having any work done. The selected answer seems like the PM is doing everything without even talking with the team, and that's a recipe for failure.
Source: Adapted from community discussion — [Removed]