Question 631 · 1401 in bank
A project team was hired to perform on-site duties, but there were unexpected circumstances that required the entire team to work remotely. Some team members returned to their hometowns, and they are now requesting reimbursement for operational expenditures. What should the project manager do?
Show answer
Answer: D
Explanation
When there are unexpected changes in the project, such as the shift to remote work and the resulting operational expenditures, the project manager should follow the Perform Integrated Change Control process. This involves submitting a change request to assess the impact of the change on the project budget, timeline, and resources. Once the change request is evaluated and approved by the appropriate stakeholders, the project manager can proceed with any necessary adjustments to the budget, project management plan, or reimbursement policies. Options A, B, and C do not follow the established change control process and may result in inaccurate budgeting or improper handling of project funds.
Source: Adapted from community discussion — Alizade