Question 1251 · 1401 in bank
A project team is engaging a development team in another country to develop software. During progress reviews, the project manager identified completion date delays due to rework because there were different interpretations of the client's needs. What should the project manager do?
Show answer
Answer: D
Explanation
I think the answer is A. This question is talking about the unclarity of the requirement. So the best option is to clarify the requirement with stake holders. If you go with answer D, again rework may be expected on the prototype until the requirement is clear and all are on the same page.
Source: Adapted from community discussion — rajeshtk