The project manager of an agile project has been asked to reduce the budget by 30%. Since this is a small project team, the budget is primarily allocated to resources. What strategy should the project manager use in order to keep delivering value in a restricted environment?
Show answer
Answer: C
Explanation
C is answer. The question does not mention that PM is person who prioritize backlog. It only says that what strategy should be used.