Question 1281 · 1401 in bank
Select 2A project manager for an agile project is concerned that the team has been losing momentum over the last iterations. Which two tools should the project manager use to analyze team performance? (Choose two.)
Show answer
Answer: AC
Explanation
A. Burndown chart: The burndown chart tracks the progress of work completed against the planned work over time. It provides a visual representation of the team's progress and helps identify any deviations from the planned trajectory. By analyzing the burndown chart, the project manager can assess whether the team is falling behind, maintaining a steady pace, or accelerating, allowing them to take corrective actions if necessary. C. Cumulative flow diagram of completed features: The cumulative flow diagram tracks the flow of work items through different stages of the project. It provides a visual representation of the work in progress and can highlight bottlenecks or areas where work is piling up. By analyzing the cumulative flow diagram, the project manager can identify any blockages or inefficiencies that may be hindering the team's momentum and take steps to address them.
Source: Adapted from community discussion — AbbasTaki