Question 1311 · 1401 in bank
Select 2A project manager is assigned to a project that is in development. As the project manager reviews the project's progress, they find a few tasks that are behind schedule. After investigating, the project manager discovers that a few team members were pulled to work on other assignments, which impacted their ability to focus on the project manager's project. Which two actions can the project manager take to bring the team back on track? (Choose two.)
Show answer
Answer: DE
Explanation
D. Discuss the risk of project delay and work priorities with the respective functional managers E. Work with the team to identify options to accelerate project delivery