Question 51 · 1401 in bank
A few key team members recently left the project team. The remaining members took time to understand the details and found it difficult to make progress. As a result, the project schedule is seriously delayed. What should the project manager do?
Show answer
Answer: D
Explanation
In this situation, the most appropriate action for the project manager would be: D. Review the issues and adjust the project plan to give a realistic schedule. Escalating to the project sponsor is a viable option, but it is typically more effective after internal efforts to adjust and manage the situation have been explored. Directly escalating could imply that the project manager hasn't taken sufficient steps to manage the situation at their level.
Source: Adapted from community discussion — Delab202