A project manager has just been hired by a company without a project management governance structure. During the kick-off meeting, a key stakeholder emphasizes the importance of the project meeting the company's strategy, investment, and compliance requirements. What should the project manager do?
Show answer
Answer: A
Explanation
A is the correct Answer The PM got some direction from the Sponsor and with that he can at least establish a Governance Model for the project to begin with. Remember he can at least control within his capacity around his project but can't do Option "C" as it is at the org level. "D" is shying away from his responsibilities so "A" is the best choice among all these.