During project execution, a key resource leaves the team for another job. What should the project manager do in this situation?
Show answer
Answer: C
Certified Associate in Project Management497 questions across 50 pages are complete and free, with no account or card.
497 questions in this bank
Free access · progress saved on this device
During project execution, a key resource leaves the team for another job. What should the project manager do in this situation?
Answer: C
During the project planning process, which three of the following stakeholders are required to take part in the risk assessment meeting? (Choose three.)
Answer: ACD

Vicus (team member) mentions they do not have enough market information to make proper decisions. Verna (agile facilitator) confirms it is because no one on the team understands the Asian market. Verna suggests to replace some team members, as they need to recruit team members that are familiar with the Asian market. What type of agile team would they be composing, with diverse skills and experience, who collectively have all the skills the team needs to fulfill its purpose?
Answer: A
A business manager wants to start a project to launch a new product. How should the manager initiate the project?
Answer: C
A business analyst is working on a project that follows an adaptive life cycle. Due to budgetary constraints, the sponsor asks the team to focus on critical requirements. What should the business analyst do?
Answer: B
What tool can be used to track how involved and interested stakeholders are in a project?
Answer: A
A production support system is being managed by a team. The team members cannot plan their work in advance, even for a week, because they do not know when new support issues will be submitted. The team cannot start working on new issues until they finish existing issues, no matter how long it takes to finish the existing issues. Which method should be used in this situation?
Answer: B
An adaptive team's velocity dropped significantly in the last sprint due to the planned vacation of two team members. The project sponsor wants to know how many more sprints it would take to complete the remaining project. How should the project manager calculate the anticipated velocity for future sprints?
Answer: D
A new business analyst has joined the team in the middle of a project and the requirements traceability matrix has been updated. What should the business analyst do next?
Answer: B
A project manager is assigned to a project, and the sponsor signals to perform first actions. However, the project manager is unsure how to apply organizational resources into project activities before a formal authorization. Which document should be used in this case?
Answer: B