Question 31 · 1401 in bank
Halfway through a project, the project sponsor is replaced by another peer who was not previously engaged in the project. The new project sponsor has rejected most of the project artifacts, and the team did not get the latest increment approved on the current iteration. Stakeholders are not feeling confident about the project outcome. What should the project manager have done to prevent this situation?
Show answer
Answer: A
Explanation
I chose D. But after read the correct answer and question. the question focuses on preventing this situation from happening in the future, rather than finding a solution to the current problem. With this mindset, "A. Performed a stakeholder analysis when the sponsor joined the project" is indeed worth considering.