Question 291 · 1401 in bank
The testing backlog for a hybrid project has increased significantly and is becoming a bottleneck. The team has researched a tool that could resolve the bottleneck, and the project manager has been informed. What should the project manager do next?
Show answer
Answer: D
Explanation
Out of 1200 questions so far, I think "Escalate" was the correct answer on only 1 occasion. I don't believe it is correct here. The "softest" step is to Enroll team members in training.
Source: Adapted from community discussion — d370e49