During an iteration, an urgent customer request for support reaches the team. If they work on it, the team's commitments in this iteration are at risk. What should the team do next?
Show answer
Answer: C
PMI Agile Certified Practitioner341 questions across 35 pages are complete and free, with no account or card.
341 questions in this bank
Free access · progress saved on this device
During an iteration, an urgent customer request for support reaches the team. If they work on it, the team's commitments in this iteration are at risk. What should the team do next?
Answer: C
What information should a project team include in an extended stakeholder report to ensure that all current and future stakeholders are aware of the frequent updates?
Answer: D
A project team has a senior subject matter expert (SME) who is comfortable with data integration. The SME is not inclined to perform regression testing because the SME feels that performing regression testing is more of a junior duty. What should the scrum master do?
Answer: D
A new agile project leader habitually becomes involved in the work from a support perspective and uses information radiators to ensure that all actions to remove impediments are visible to the team. What is the agile project leader doing?
Answer: A
Based on the backlog metrics in the chart, what can explain the jump in points at the end of iteration 4?
Answer: C
A product owner has various items in a product backlog and does not know how to prioritize them. How should the agile practitioner coach the product owner?
Answer: B
At an iteration review, the product owner indicated that the work delivered did not meet expectations. The project team is surprised. How should this situation have been prevented?
Answer: A
A. Reviewing the definition of done prior to the iteration review could have been a crucial step to ensure alignment between the delivered work and the product owner's expectations.
Source: Adapted from community discussion — melki_zedek
A company has decided to use an agile delivery method for launching a new product to improve the customer checkout experience. How should the project manager ensure the experienced predictive delivery teams are capable of adopting the agile model?
Answer: B
B = correct. The organization is willing to adopt the Agile approach. Thus, it is essential for all of the stakeholders to understand the Agile principles. This is unrelated to the Agile development team (otherwise A would be the correct option).
Source: Adapted from community discussion — Petrevski
The team is derailed by a demand from a senior manager unrelated to the project. How does the agile coach help the team?
Answer: D
After conducting the second retrospective with project stakeholders, the customer expresses frustration. The customer wants a more predictable roadmap for the delivery of features and functionalities. How should the project manager respond to the customer?
Answer: C
Both C and D can be correct. Regularly, only the PO prioritizes the backlog, however, I like C cause it's a more comprehensive response.
Source: Adapted from community discussion — janojano