Question 111 · 341 in bank
An agile team is unable to complete all its planned sprint user stories, which results in a decrease of its planned sprint velocity. What should the team do?
Show answer
Answer: D
Explanation
D is make sense. Once stories get completed it is useless to re estimate them again, the team should always focus on stories not yet completed for prioritization and refreshing the backlog before starting the next sprint.
Source: Adapted from community discussion — snow5