Question 161 · 341 in bank
A customer has difficulty explaining how the highest priority feature will work. What should the agile project manager do?
Show answer
Answer: D
PMI Agile Certified Practitioner341 questions across 35 pages are complete and free, with no account or card.
341 questions in this bank
Free access · progress saved on this device
A customer has difficulty explaining how the highest priority feature will work. What should the agile project manager do?
Answer: D
During a review close to a product release, the customer spotted several features that will need to be changed. What caused this to happen?
Answer: A
Select Answer: A Without customer collaboration, the team will not understand the customer's needs and preferences and, thus, may not develop the right product.
Source: Adapted from community discussion — MattAnya
An organization wants to execute a corporate website redesign project using Scrum. There is an experienced pool of agile team members from a previous project, as well as a pool of available internal team members with some Scrum background. What should be considered when selecting the team?
Answer: B
Some members of an agile project team work remotely, so it is difficult to have regular face-to-face backlog grooming sessions. How should the agile practitioner ensure that the team is able to reduce miscommunication and rework in this environment?
Answer: C
During a project's last iteration, an agile team struggled with a feature's delivery due to the lack of a required skill. The project has already incurred a five-day delay. A further delay of at least 10 days is anticipated. What should the agile project leader have done to avoid this situation?
Answer: D
A project team is currently working on sprint seven of a release that is estimated to require twelve sprints to complete. The team has reviewed the stories for this sprint and discovered that it will require rework from previous sprints. What should the scrum master do?
Answer: D
While working on a sprint for a software development project, the team is unsure of how the feature should be designed. The project sponsor recommends developing a prototype of the user interface to discover more about this feature. Why is the project sponsor making this suggestion?
Answer: C
So instead of creatingvery detailed specifications andplans, agileprojects build aprototype to better understand the domain anduse thisprototype as thebasis for furtherplanningand elaboration. C
Source: Adapted from community discussion — Tonome
Midway through a sprint, a team member discovers that the product design fails to adhere to the organization's enterprise architecture standards. Since this required escalation to the architecture team for further analysis and resolution, the team was unable to deliver its sprint goal and the sprint was cancelled. What should the team have done to avoid this?
Answer: B
Just out of curiosity, who provides these answers, and why are so many of them wrong. It seems it is done on purpose to confuse people and make mistakes during the exam...
Source: Adapted from community discussion — Alex1904
An agile team wants to collectively determine a project's size. What will the team be doing if they use the planning poker technique to accomplish this?
Answer: D
A team is preparing to demonstrate new product capabilities to a leadership team. The demonstration will show working software and a listing of the projected value of the capabilities. What should the team do to ensure the demonstration is successful?
Answer: B
Keyboard:J Kmove between questionsA–Dselect an answerRshow or hide the answer← →change page
PMI-ACP practice, question 161. 341 questions available.
Version 1.0.0. How we source questions