Question 91 · 341 in bank
An agile team and a traditional development team are working together on a project. Each team exceeds expectations regarding deliverables; however, issues arise when the deliverables are integrated. What should the agile practitioner do?
Show answer
Answer: A
Explanation
The best answer is A. Foster stronger communication by hosting cross-organizational meetings between the two teams. Explanation: The issue of integration suggests that there is a lack of communication and collaboration between the two teams. Hosting cross-organizational meetings will allow both teams to discuss their progress, identify any potential issues, and work together to find solutions. This will also help build trust and understanding between the teams, which is essential for successful integration. Option B, suggesting merging the teams, may not be feasible or practical as it could lead to larger team sizes and potential conflicts in working styles. Option C, creating stories from full technical specifications, may not address the underlying issue of communication and collaboration between the two teams. Option D, co-locating the teams, may not be possible if they are located in different geographical locations or if it disrupts their established working arrangements
Source: Adapted from community discussion — SohaibMahmoud