When working on a new product, what should an agile team do to ensure alignment with external stakeholders?
Answer: B
On an agile project, it is important to identify and engage business stakeholders throughout the project and to ensure the team understands the stakeholders' business needs. Which option supports this idea?
Answer: B
A high-profile project team is struggling to meet planned velocity. During a retrospective, the team agreed that their lack of experience in the technology resulted in an excess of rework. What should be done to resolve this challenge?
Answer: D
During a retrospective, the team agrees that they have limited competence in using a newly introduced tool. What should the team do?
Answer: A
The agile lead is told by executive leadership that the team needs to work faster because the release date has been moved up three months. The agile lead communicates the updated timeline to the team. One of the junior team members objects and feels the timeline is unrealistic. What should the junior team member do?
Answer: D
A = correct There is one member with an objection to the update timeline. There's no team consensus regarding this question. Thus, that member has to speak with the Agile lead - he has to facilitate the updated timeline understanding to the member. B, C = not an agile approach D = explained above
Source: Adapted from community discussion — Petrevski
After performing three sprints, the product owner and sponsor request an accurate schedule indicating when all releases will be delivered. What should the agile practitioner do?
Answer: D
A software project is being implemented by a small, colocated team. What should the project manager do to keep the team focused and engaged with the high level of requirements?
Answer: D
An agile team is having difficulties in obtaining the participation of a true user to be a part of their team. In the absence of a true user, the development manager steps in to act as a proxy for the user. What can the agile team do to improve value delivery in the absence of a true user?
Answer: D
A team is transitioning from a predictive approach to an agile approach. Historically, the team has delivered work products that did not meet customer expectations. What agile practice can help the team to alleviate this?
Answer: B
A project has several features that will deliver immediate customer value. The product owner needs to determine which features to include in the upcoming iteration. What should the product owner have the customer review and approve?
Answer: C