Question 801 · 1401 in bank
A project manager is leading an electrical project that spans five towns. The project manager is informed by the team that one of the towns is not allowing the team to work there even though the town was included in stakeholder engagements before the start of the project. What should the project manager do?
Show answer
Answer: A
Explanation
The best course of action for the project manager in this situation would be option A: Engage with the town's authorities to discuss the reason for the change in commitment and agree on a solution. Engaging with the town's authorities can help the project manager understand why the town is not allowing the team to work there and find a solution that is acceptable to both parties. It is possible that there has been a change in the town's circumstances that has led to the change in commitment, and this needs to be understood and addressed.
Source: Adapted from community discussion — Alizade