Question 741 · 1401 in bank
A project manager is tasked with developing a coaching model to support and recognize team members' growth. What should the project manager consider when defining their coaching strategy?
Show answer
Answer: A
Project Management Professional1,401 questions across 141 pages are complete and free, with no account or card.
1401 questions in this bank
Free access · progress saved on this device
A project manager is tasked with developing a coaching model to support and recognize team members' growth. What should the project manager consider when defining their coaching strategy?
Answer: A
During a sprint, one of the team members found an issue. According to the team member and the product owner, the issue has a higher level of importance than the other features of the sprint, but is not a roadblock to completing it. What should the project lead ask the project team do?
Answer: D
A team realizes that there is no access to data that the project depends on to complete the current iteration. This dependency was known; however, the team is unsure of the available options to remove this obstacle. What should the project manager do next?
Answer: B
A project's customer is furious. When the customer arrived at the project site, they discovered that one of their requirements was not met. What should the project manager do?
Answer: B
Requirement not met means it was already defined in planning during Define Requirement Process before Create Scope Statement Process. A requirment traceability matrix should be consulted to have more information on this requirment and how it is linked to other artifacts of the project.
Source: Adapted from community discussion — achacyrille
An internal virtual team is meeting daily to review iteration progress, as well as to conduct other technical and follow-up calls with key stakeholders. The team seems to be disengaged. How should the project manager approach this situation?
Answer: B
An external project manager is managing the construction of new corporate offices for a large company. The project management plan states that it is necessary to contract a highly trained external resource to revise and validate an important project component. The client has rejected hiring the external resource because of the high cost, even though it is within the project budget. What should the project manager do to resolve this issue?
Answer: C
A major public-transportation construction project is aimed at significantly reducing emissions. The project has been severely delayed due to noncompliance with environmental codes and bylaws. What should the project manager have done to prevent this?
Answer: D
The project team is experiencing schedule delays due to issues arising with suppliers. Some of the tasks are on the critical path. What should the project manager do in this situation?
Answer: B
B. Due to the tasks being on the critical path, the PM should review the critical path to see the impact, so that it can be discussed with stakeholders to determine the next steps or risk strategy. I believe that you would only discuss with procurement once a decision is made on the way forward.
Source: Adapted from community discussion — Baj2023
Project acceptance criteria include on-site training for the new users of a system. Due to unforeseen circumstances, all team members have to work remotely for an indefinite period of time. What should the project manager do?
Answer: B
In a daily standup meeting, a project manager notices that a team member's reports include incomplete tasks with no impediments. A colleague informs the project manager that this team member is experiencing a personal issue. What should the project manager do?
Answer: D
D. Understand the team member's personal issue and offer them support. As a project manager, it's important to be empathetic and supportive towards team members who are experiencing personal issues that could affect their work performance. The first step is to approach the team member in a private and confidential manner to understand the issue and offer support. The project manager should also reassure the team member that their health and wellbeing is a priority and encourage them to take any necessary time off or work flexibly if it would help them deal with their personal issue. In addition, the project manager may need to reassign some of the team member's tasks temporarily to ensure that the project progresses as planned while the team member gets the necessary support.
Source: Adapted from community discussion — Alizade