Question 851 · 1401 in bank
After the project charter's approval, the project manager needs to work on detailed project requirements, constraints, and assumptions with stakeholders. However, not all of the stakeholders are immediately available for a meeting in the short term. What should the project manager do in order to gather the information needed from stakeholders?
Show answer
Answer: B
Explanation
B. Email, call, or meet with each stakeholder separately to obtain their input. Since not all stakeholders are available for a meeting, the project manager should reach out to them individually to gather the necessary information. This could be done through emails, phone calls, or individual meetings. It is important to ensure that all stakeholders have an opportunity to provide input to ensure that the requirements, constraints, and assumptions are properly identified and documented.
Source: Adapted from community discussion — Hung3102