Question 781 · 1401 in bank
A customer reviewed the plan for a project with high uncertainty. The customer expressed concerned about the work requiring so many iterations with a risk of not reaching the mandatory delivery date. Which approach should the project manager use in this situation?
Show answer
Answer: C
Explanation
The project manager should use C. Hybrid approach. This approach combines elements of both predictive (or traditional) and Agile methodologies. It allows for flexibility in areas of high uncertainty (where Agile shines) while maintaining a level of predictability for certain aspects of the project (where traditional methods are beneficial). This can help manage the customer’s concerns about the risk of not reaching the mandatory delivery date due to numerous iterations.
Source: Adapted from community discussion — josephsafiran