An agile team is working on a new product. To ensure that all unknown issues are clarified before committing to the scope, the team plans to work only on spike user stories for the next three sprints. What should an agile coach do in this situation?
Show answer
Answer: C
Explanation
focusing exclusively on spikes for three sprints may slow down overall progress. Balancing spikes with delivering features helps in managing both risks and value delivery simultaneously.