What duration compression technique typically adds risk when it's used during a program?
Show answer
Answer: B
Program Management Professional439 questions across 44 pages are complete and free, with no account or card.
439 questions in this bank
Free access · progress saved on this device
What duration compression technique typically adds risk when it's used during a program?
Answer: B
A program receives initial approval from the selection committee to proceed with the program development. What should the program manager do next?
Answer: D
You are the program manager for your organization. Management has asked that you determine when resources, such as leased equipment, are no longer needed so that you may release the resources to save time, money, and utilization of resources within your program. What program management process is management asking you to perform?
Answer: B
The program manager of a multinational program must reconcile data including subject matter experts' labor hour estimates, and other direct resource hour estimates. In addition, the program manager must prepare the cash flow analysis. Which of the following should be considered to get a baseline budget?
Answer: B
A key stakeholder's requirement contradicts the organization's strategic objectives. The program manager meets with the stakeholder, but is unable to reach a compromise on the requirement. What should the program manager do first?
Answer: C
Near the completion of a transformation program, the operations manager is concerned that their department failed to be notified in advance of the new service being transitioned into operations. They claim that their department did not approve this service, and is now unprepared and untrained to support the transformation. What should the program manager have done first to prevent this?
Answer: B
A program stakeholder is concerned about information they receive about a project. Who is responsible for reviewing the communications management plan to assure adequate information is provided to the stakeholder?
Answer: D
In the case where a program stakeholder is concerned about the information they receive about a project, the responsibility for reviewing the communications management plan to ensure adequate information is provided to the stakeholder falls on: D. Program manager. The program manager is responsible for the overall coordination and management of the program, which includes ensuring that communication strategies are effectively implemented. This responsibility involves overseeing the communications management plan and making sure that it addresses the information needs of all stakeholders. While the project manager, communications manager, and program sponsor play significant roles in communication, it is the program manager who ultimately ensures that the communication plan is adequate and effectively executed across the program.
Source: Adapted from community discussion — happykaur
A program manager prepares the program for review to secure funding by senior management. Which of the following must the program manager identify when creating the program charter?
Answer: D
A newly appointed country manager suggests that the regional program manager use a social media platform to expedite communications and address questions. The new country manager used this social media platform at a previous job. What should the regional program manager do to address the country manager's request?
Answer: D
I still think D is the right answer. A regional program manager to start reviewing in house social capabilities could be a distraction, plus may not make the best decision. It should be left to corporate technology, security teams to review and advise on fitment.
Source: Adapted from community discussion — psvexam
A program manager for the construction of an international event venue that will impact the local community needs to determine the best approach for communications. One of the conditions of the program is that after the event takes place, a park will be built for the community's use. What should the program manager do to ensure community support?
Answer: B