What actions are taken in the process of developing and maintaining a program risk register?
Show answer
Answer: B
Program Management Professional439 questions across 44 pages are complete and free, with no account or card.
439 questions in this bank
Free access · progress saved on this device
What actions are taken in the process of developing and maintaining a program risk register?
Answer: B
A hotel chain initiates a program to expand meeting offerings to include telecommunications technology and virtual meetings. The program has component projects, each of which requires team members to have different technical skills and expertise. The program manager assembles a team of project managers to lead each of the projects, and learns that the desired resources will not be available at the start of the program. As a result, the program manager must do which of the following?
Answer: D
A company is releasing a new product geared toward a specific geographic area. The program manager has received the program objectives and developed the program roadmap, which consists of six program components. Approval from the program governance board has been obtained. What is the program manager's next step?
Answer: A
A. Assign project managers and resources Once the program objectives have been set, the program roadmap developed, and approval from the program governance board obtained, the next logical step for the program manager is to assign project managers and resources to the program components. This is a crucial step in ensuring that each component of the program has the leadership and resources necessary to proceed with the detailed planning and execution of their respective parts. This allocation of project managers and resources will facilitate the effective and efficient implementation of the program according to the established roadmap and objectives.
Source: Adapted from community discussion — [Removed]
A project is assigned to a qualified project manager by the program manager. The client rejects the project manager due to a lack of proper qualifications to manage such a project. What should the program manager do next?
Answer: C
A program manager concurrently implements a software program at four client locations. The client's objective is to maintain quality while shortening the software implementation timeline. What key elements should be included in the benefits register to achieve this goal?
Answer: D
Olive is the program manager for her organization. She has created a request for proposal for a large portion of her program. In this work to be procured she has set several requirements for the vendors to participate. The chief among these requirements is a vendor must have at least four licensed electricians in his team. This requirement for four licensed electricians is an example of which one of the following terms?
Answer: A
The requirement for at least four licensed electricians in the team is an example of "D. Evaluation criteria." Evaluation criteria are the specific standards or requirements that are used to assess and evaluate proposals or bids submitted by vendors in response to a request for proposal (RFP). In this case, the number of licensed electricians is a specific criterion that the vendors must meet to be considered for the program.
Source: Adapted from community discussion — mfshabana
Your program has been selected and its program charter is now being created. The program charter defines all of the following characteristics except for which one?
Answer: D
A natural disaster shuts down operations for two days. The program has a major milestone that includes a timed payment of US$1 million. Since the shutdown was not anticipated, what should the program manager do first?
Answer: C

The above performance report shows the earned value (EV) analysis for a program. The program director performs a high-level analysis and must present a summary narrative to the steering committee. What do the current findings show?
Answer: D
A large automaker begins a program to create the next-generation car. As the program team is composed, key stakeholders are identified. Key stakeholders for the program should include which of the following?
Answer: A