Question 241 · 289 in bank
HOTSPOT - You plan to create a Power BI dataflow. The Power BI dataflow has the following requirements: • Be able to create a copy of the dataflow to separate Power BI workspaces. • Schedule the dataflow to update every day at 11:00 AM. You need to configure the dataflow. What should you do? To answer, select the appropriate options in the answer area. NOTE: Each correct selection is worth one point.

This is an interactive task on the real exam — a drag-and-drop, hotspot or ordering question. There is nothing to select here, so the answer is shown below for reference.
Show the answer figure
Answer: See figure below
Explanation
Had the same question, when reading again, this is a Power BI dataflow, not a dataflow in PowerApps, then, yes refresh in Power BI Service
Source: Adapted from community discussion — [Removed]