A company is implementing a new radar system from July to September. The project manager knows these months are the peak hurricane season for this region. Which of the following should the project manager develop to mitigate the risk to the project?
Show answer
Answer: B
Explanation
A Contingency Plan is indeed the recommended action when a project faces potential risks like hurricane season during its implementation . A contingency plan allows for proactive management and preparation for potential adverse effects of such risks, ensuring the project's ability to adapt or recover swiftly should the risks materialize.