Question 121 · 384 in bank
Which of the following is an activity that should be used in the closing phase of a project to support the project triple constraint?
Show answer
Answer: D
Explanation
D. Reconciling the budget is an activity that should be used in the closing phase of a project to support the project triple constraint. The project triple constraint refers to the relationship between scope, time, and cost in a project. Reconciling the project budget at the closing phase of a project ensures that all expenses have been accounted for, and the final budget is reconciled with the actual expenses, which is crucial to measuring cost performance. Evaluating the project is an activity that should be conducted throughout the project and not just in the closing phase. The purpose of evaluating the project is to determine whether the project was a success or failure, or if there are any areas that require improvement.