Question 911 · 1401 in bank
A project manager is tracking a project, but a key stakeholder will not accept the project's key performance indicator (KPI) results. Which tool or technique should the project manager use?
Show answer
Answer: B
Explanation
B. Expert judgment When a key stakeholder will not accept the project's key performance indicator (KPI) results, the project manager should use expert judgment. This involves seeking the advice and guidance of a person or group of people who have the knowledge and experience to evaluate the situation and provide an objective opinion. The project manager should consult with the expert to understand the reason for the stakeholder's dissatisfaction, and to determine if there is a valid issue with the KPI results or if it is a matter of perception or communication. Using change control tools may not be the best approach since the project manager has not identified any changes, using autocratic decision making may not take into account the stakeholder's perspective or the expert's opinion, and a context diagram is a visual representation of the system and its environment but it's not useful in this case.
Source: Adapted from community discussion — Adeshola1960