Question 1151 · 1401 in bank
A project manager for a software technology project works in a matrixed organization with virtual teams. Unfortunately, the functional manager informs the project manager that there may not be any resources available to test the software. What should the project manager do next?
Show answer
Answer: B
Explanation
I think B is a better answer because of the keyword "matrixed organization". The person who raised the resource issue is the Functional manager. Option C talks about coming up with a better approach in testing but the issue is [there may not be any resource]. Unless you skip testing entirely.. the best testing approach still need resource.
Source: Adapted from community discussion — alltaken