Question 1081 · 1401 in bank
An agile project manager would like to convert the requirements document into epics, capabilities, features and stories. In how many iterations should the project manager estimate the story duration?
Show answer
Answer: B
Explanation
The correct answer is B. One iteration. In agile frameworks, user stories are the smallest unit of work and they are designed to be completed within a single iteration or sprint. So, when estimating the duration of a user story, it should fit within one iteration. If it's too big to be completed in a single iteration, then it should be broken down into smaller user stories.