Question 371 · 439 in bank
A program consists of four projects and three of those projects are executed by an outsourcing company as it requires specialized skills that are only available with the outsourcing company. The program is considered high risk as the organization has never implemented such a program before. During the initial executive steering committee meeting, one of the key influential stakeholders has concerns regarding the risk management process for this program. What should the program manager do to alleviate the stakeholder’s concerns?
Show answer
Answer: B