Question 31 · 384 in bank
A stakeholder notices a typo in the project management plan, specifically the word manager was spelled “manger”. Which of the following is the decision maker who can authorize the change so the correction can be made?
Show answer
Answer: A
Explanation
For a typo as minor as this one in the project management plan, the decision maker who would most likely authorize the change for the correction would typically be "A. PM" (Project Manager). In many organizations, small changes like correcting typos usually fall under the authority of the Project Manager and do not require formal approval from higher-level entities like the Change Control Board (CCB) or the project sponsor.